MEDIUM TERM SURFACE FACILITY EXPANSION PROJECT – FAHUD

Process Design Verification, Existing Pipeline Demolition, New Pipelines Installation, Tie-in Details, and Safety Zone Classification.



Client Galfar Engineering & Contracting SAOG is one of the largest, multi-disciplined engineering, contracting and construction company in the Sultanate of Oman. Established in the year 1972, Galfar Engineering & Contracting SAOG, has today grown into one of the largest construction companies in the Middle East with a turnover of over US$1 billion. Galfar, has the experience and expertise in project management, engineering, procurement and construction in areas like Oil & Gas, Civil, Electro-Mechanical, Roads & Bridges and Environmental projects. The range of projects executed includes oil and gas pipelines, oil and gas production, collection and processing facilities, service contracts in petroleum industry.
Customer Petroleum Development Oman is the foremost exploration and production company in the Sultanate. It accounts for more than 70% of the country’s crude-oil production and nearly all of its natural-gas supply. PDO finds oil fields and develops them into productive assets by drilling wells and constructing and operating various hydrocarbon treatment and transport facilities. The crude oil that is produced from the fields is not sold by the Company but rather delivered to a storage facility at Mina al Fahal, where it is loaded onto sea-going tankers at the discretion of the Company’s shareholders. PDO also finds, develops and operates natural-gas fields and their associated production systems-all on behalf of the Government of Oman.
Location Fahud area, Oman
Duration 8 Weeks
Deliverables
  • Process Engineering Flow Schemes
  • Process Design Basis
  • Site Visit Report
  • Process Datasheets for ESDVs
  • Tie-in Philosophy
  • Hazardous Area Classification Drawings
 
Design Data / Specifications
Destination: Fahud – C to Fahud – F
Fluid Type: LP gas
Pipeline Length: 2.1 km
Pipeline Life: 20 years
Maximum Liquid flow: 125 ks m3/day

Destination: Fahud – D to Fahud – F
Fluid type: LP gas
Pipeline Length: 0.5 km
Pipeline Life: 20 years
Maximum Liquid flow: 650 ks m3/day

Destination: Fahud – F to Fahud – D
Fluid type: HP gas
Pipeline Length: 1.2 km
Pipeline Life: 20 years
Maximum Liquid flow: 1500 ks m3/day

Facilities / Modules Designed
Pipe Lines